PROJECT EXPERIENCE

Peckham Rye Gyratory Improvements, London

PROJECT DATE

July 2020

07 / 09

Context & contribution

Project context

Walking and cycling improvement proposals along Peckham Rye East, forming part of the wider Cycleway 35 corridor and Southwark Council’s active travel objectives.

My contribution

  • Contributed to highway layout development using AutoCAD.
  • Worked on proposals for segregated cycle lanes and an informal pedestrian crossing.
  • Supported the development of connections between Peckham High Street and Nunhead Lane within the wider scheme.

Working context

This project forms part of my earlier professional experience. My contribution covered the tasks described here within a wider project team.